What is the time limit for claims under a contract by deed?

Prepare for the NEBOSH General Certificate. Access flashcards and multiple choice questions with detailed explanations to enhance your understanding of occupational health and safety norms. Boost your exam readiness today!

The correct answer is that the time limit for claims under a contract by deed is 12 years. This duration is established by the Limitation Act 1980, which outlines the time limits for making claims in various circumstances.

In the context of contracts executed as deeds, the law provides a longer limitation period compared to unsealed contracts, which typically have a limitation period of 6 years. The rationale behind this extended timeframe is that deeds represent more formal agreements and are typically subjected to higher standards of execution and intention. This aligns with the perspective that parties entering into such formal agreements may require a longer duration to discover breaches or to seek redress when disputes arise.

Understanding this distinction and the specific timelines is crucial for professionals in occupational health and safety, among other fields, as it can significantly impact the management of contractual obligations and the pursuit of claims related to obligations arising from those contracts.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy